In: Refurbishment

Fullwell Cross Library / 504k, 20 weeks / Redbridge, Essex

This was the refurbishment of a listed building that was unusual in design as the building was circular and solid concrete. The refurbishment involved stripping out and saving existing book shelves. Forming a new aluminium front entrance with lobby, rear ramp in garden with new handrail.

  • Inside we refurbished both public and staff toilets,
  • refurbished the children’s library,
  • the main library including new power and data 2nd fix for specialist contractors to 1st fix.
  • New carpet tiles to all areas.

This was a 15 week project that ran to 20 as we had 2 severe weather fronts that set us back 3 -5 weeks.